Wednesday, March 12, 2014

CCNP Route 640-902 Exam Topics Compared


642-902 Exam Objectives:

1.0 Implement an EIGRP based solution, given a network design and a set of requirements
2.0 Implement a multi-area OSPF Network, given a network design and a set of requirements
3.0 Implement an eBGP based solution, given a network design and a set of requirements
4.0 Implement an IPv6 based solution, given a network design and a set of requirements
5.0 Implement an IPv4 or IPv6 based redistribution solution, given a network design and a set of requirements
6.0 Implement Layer 3 Path Control Solution
7.0 Implement basic teleworker and branch services

642-901 Objectives (Old):

1. Describe and implement EIGRP operations
2. Describe and  implement multiarea OSPF oprations
3. Describe integrated IS-IS
4. Describe and implement Cisco IOS routing features
5. Implement BGP for enterprise ISP connectivity
6. Describe IP multicasting
7. Configure and verify multicast forwarding
8. Configure route filtering and redistribution
9. Describe and implement IPv6

Mapping of old and new exam objectives:
1 (EGRP)        ---- 1
2 (OSPF) ----2
3 (IS-IS) -- Removed in the new Route Exam
4 (Implement Cisco IOS routing features) --> 4, Describe and implement Cisco IOS routing features and  8. Configure route filtering and redistribution
5 (BGP for enterprise ISP connectivity) --> 5
6 (Multicast) --> Removed in the new Route Exam
7 (Implement IPv6) --> 9

There are a few new topics in IPv6 implementation, otherwise, there seems to be nothing new in 902 version compared to it's predecessor 901.
CCNP Route 640-902 Practice Tests 

642-902 Exam Objectives:

Implement an EIGRP based solution, given a network design and a set of requirements

 Determine network resources needed for implementing EIGRP on a network
 Create an EIGRP implementation plan
 Create an EIGRP verification plan
 Configure EIGRP routing
 Verify EIGRP solution was implemented properly using show and debug commands
 Document results of EIGRP implementation and verification

Implement a multi-area OSPF Network, given a network design and a set of requirements

 Determine network resources needed for implementing OSPF on a network
 Create an OSPF implementation plan
 Create an OSPF verification plan
 Configure OSPF routing
 Verify OSPF solution was implemented properly using show and debug commands
 Document results of OSPF implementation and verification plan

Implement an eBGP based solution, given a network design and a set of requirements

 Determine network resources needed for implementing eBGP on a network
 Create an eBGP implementation plan
 Create an eBGP verification plan
 Configure eBGP routing
 Verify eBGP solution was implemented properly using show and debug commands
 Document results of eBGP implementation and verification plan

Implement an IPv6 based solution, given a network design and a set of requirements

 Determine network resources needed for implementing IPv6 on a network

 Create an IPv6 implementation plan
 Create an IPv6 verification plan
 Configure IPv6 routing
 Configure IPv6 interoperation with IPv4
 Verify IPv6 solution was implemented properly using show and debug commands
 Document results of IPv6 implementation and verification plan

Implement an IPv4 or IPv6 based redistribution solution, given a network design and a set of requirements

 Create a redistribution implementation plan based upon the results of the redistribution analysis
 Create a redistribution verification plan
 Configure a redistribution solution
 Verify that a redistribution was implemented
 Document results of a redistribution implementation and verification plan
 Identify the differences between implementing an IPv4 and IPv6 redistribution solution

Implement Layer 3 Path Control Solution

 Create a Layer 3 path control implementation plan based upon the results of the redistribution analysis
 Create a Layer 3 path control verification plan
 Configure Layer 3 path control
 Verify that a Layer 3 path control was implemented
 Document results of a Layer 3 path control implementation and verification plan

 Implement basic teleworker and branch services


 Describe broadband technologies
 Configure basic broadband connections
 Describe basic VPN technologies
 Configure GRE
 Describe branch access technologies

CCNP Route

CCNP Switch

No comments: